Cleanroom energy saving options: set-back, fans, filters and air volume

The main saving options are to reduce air when rooms are idle, use variable-speed fans, and avoid specifying more air or a higher filter grade than the process needs. UK HTM 03-01 says there is no aerobiological benefit in running ultra-clean theatre fans when the theatre is not in use, and that variable-speed recirculation fans may save energy.

By ZY Cleanroom · Updated · Sources at the end of the page

Options and where they come from

The first four rows come from HTM 03-01 Part A for hospital theatres. Check the rule of your own sector before you copy them.

OptionWhat the source saysSource
Set-back when unusedMotion sensor starts the air unit at full speed after two detections within 10 minutes. Off after 30 minutes without movement. Or set-back after 15 minutes during the working day, and off outside normal hoursHTM 03-01 paras 6.11, 6.12
Link canopy fans to the air unitCanopy fans follow the air unit to set-back or offHTM 03-01 para 6.12 note
Variable-speed recirculation fansWith differential pressure control, may suit consistent performance and energy savingHTM 03-01 para 8.98
Do not over-grade filtersGrade E10 is the minimum for the canopy. A higher grade adds fan power, energy and noiseHTM 03-01 paras 8.100, 8.101
Do not over-size air volumeAt least 20 changes per hour is typical for ISO 8 support rooms. Much higher is normal for ISO 7 and ISO 5FDA 2004
Cleanroom energy saving options: set-back, fans, filters and air volume

Limits on set-back

A room in set-back must still return to its limits when work starts. EU GMP Annex 1 gives a guidance value of under 20 minutes for the clean-up period to reach the at-rest limits (para 4.29). Test the recovery time before you fix the set-back depth.

Pressure monitoring must stay on. Annex 1 requires critical pressure differences to be monitored and recorded continuously, with an alarm (para 4.16).

ISO 14644-16:2019 gives guidance on energy efficiency in new and existing cleanrooms. Its first edition was published in May 2019. Berkeley Lab's Cleanroom Energy Programming Guide (2001) is meant for the early programming stage.

Retrofit points from HTM 03-01

When a canopy is added, an existing air unit may need work. The fan may need re-rating for the new resistance. The cooling coil may need an upgrade for return-air fans and terminal lights (para 8.95).

Return-air fan heat may need cooling inside a modular unit. The extra load is sometimes met by conditioning the primary air instead (para 8.94).

The large canopy flow means the air must be recirculated or its energy recovered (para 8.80). An alternative to motion sensors links the air unit to the lights. General lights on gives set-back. Main lamp on gives full speed. All lights off gives off (para 6.13).

How to rank the options (suggested)

Ask three questions of each option. Does it cut air volume, fan power or running hours? Does it need requalification? Does your sector rule allow it?

Options that cut running hours leave the air in use unchanged, so they are a good place to start, but a set-back mode still needs its recovery tested.

Worked example (calculated)

Assume a design cuts air from 20 to 15 changes per hour, which is 0.75 of the flow. The textbook fan law says ideal fan power falls with the cube of the flow. So 0.75³ is 0.42, an ideal drop of 58 percent.

Real plants save less. Duct and filter resistance does not scale the same way, and a fixed pressure set point holds some of the load. Use the figure to rank options, and measure the real saving on site.

The arithmetic is not an excuse to cut air. FDA says higher rates are normally needed for ISO 7 and ISO 5, so qualify the lower rate first.

If you have a room list for a project where energy matters, send it to ZY Cleanroom and we will review the panel, door and ceiling scope with you.

Questions

Common questions

Can ceiling fans be switched off at night?

HTM 03-01 says so for ultra-clean theatres, linked to the air unit control. In other sectors, qualify the recovery first.

Is a higher filter grade better?

Not by default. For theatre canopies HTM 03-01 says E10 is the minimum and a higher grade adds fan power, energy and noise.

What does ISO 14644-16 cover?

Guidance on energy efficiency in new and existing cleanrooms. It is a paid standard, so read it before you quote it.

Is the fan law saving real?

It is an ideal figure. Measure on site, because duct resistance and pressure set points reduce the gain.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.

WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.

Email: [email protected]
WhatsApp: +44 7962 561184

Step 1 of 2

WhatsAppGet a budget range