ZY CleanroomTIANJIN · SINCE 2002 Get a budget range

Buyer guide

What a cleanroom costs to run: energy, filters and testing

Running cost has three drivers: fan and conditioning energy, filter changes, and scheduled testing and monitoring. Energy is the largest in the studies cited here, and much of it moves and conditions air.

By ZY Cleanroom · Updated · Sources at the end of the page

Energy: where it goes

The LBNL figures date from 2001, so they are dated. HTM 03-01 is healthcare guidance. Treat all of these as direction, not a forecast for your plant.

SourceFinding
LBNL, 2001 (dated)Cleanroom air systems are extremely energy intensive compared with commercial buildings. Most HVAC energy goes to the recirculation system
LBNL, 2001 (dated), citing an earlier studyHVAC was 36 to 67% of total cleanroom energy in three California facilities
LBNL, 2001 (dated), citing a reviewEnergy cost could reach 65 to 75% of total annual operation and maintenance cost in Europe
HTM 03-01, 2021Fans use about 40% of all electricity in ventilation systems
ISPE Pharmaceutical Engineering, 2021Pharmaceutical cleanrooms can use up to 15 times more energy than commercial building systems, with more than 50% of electricity used by plant HVAC
What a cleanroom costs to run: energy, filters and testing

What changes fan energy

Class. In the rooms LBNL measured for its 2001 paper, recirculation fan power per area was greater at higher cleanliness for the same system type. LBNL advises against specifying more cleanliness than the process needs. ISPE (2021) lists avoiding over-specification of the class as an energy measure.

Air path. Among the ISO 5 and ISO 5/6 rooms LBNL measured, fan power ranged from 2.8 to 24.1 W/ft² (about 30 to 259 W/m², converted), more than eightfold. LBNL ties such variation to design and layout. Lower resistance in the air path means less power.

Airflow. ISPE (2021) notes that fan power depends on the cube of the airflow rate. In one LBNL case, cutting recirculated air by 10% in one ISO 4 room and 20% in another would in theory cut fan power by up to 30 to 50%. ISO 14644-16:2019 gives guidance on optimising energy use in cleanrooms.

Filter grade and fans. HTM 03-01 (para 8.101) says a higher filter grade in an ultra-clean ventilation unit adds resistance, with penalties in fan power, energy use and noise. It recommends electronically commutated fans as the most energy-efficient.

Operating mode

HTM 03-01 (paras 6.1 and 6.2) calls switching off when not needed the most efficient policy, and setting back to a minimum the next best. Para 7.12 adds that setback extends the life of filters and components.

In a sterile facility, Annex 1 (para 4.14) asks for positive pressure under all operational conditions. Any setback there needs the owner's validation.

Filters

Filter cost is the filter, the labour, the downtime and the retest. HTM 03-01 (para 11.23) asks for filter gauges marked with initial and final resistance. A coarse return filter extends the life of the terminal filter (para 8.104).

A failed leak test means replacement, or repair of a limited area (FDA, 2004). Uneven velocity across a filter is also a reason to replace it. A change of final filters is a change to consider for requalification (Annex 1, para 4.32). No source here sets a replacement interval. Ask the supplier for initial and final resistance and a design life.

Testing and monitoring

ItemInterval or modeSource
Requalification, grades A and B6 months at mostAnnex 1, para 4.32
Requalification, grades C and D12 months at mostAnnex 1, para 4.32
HEPA leak test, aseptic roomTwice a year, as an exampleFDA, 2004
Grade A particlesContinuous, at least 28 L/minAnnex 1, paras 9.16, 9.17
Critical pressure differencesContinuous, recordedAnnex 1, para 4.16

Example: lines to request, with no amounts

Example only. Ask the designer for these inputs, then cost them with your own energy and service rates.

Cost lineAsk the designer for
Fan electricityFan power at design airflow, and the full, setback and off modes
Heating, cooling, humidityCoil loads and outdoor air volume
Filter changesFilter count, initial and final resistance, expected cycle
TestingTests per room per year, and who performs them
MonitoringSensors, counters and calibration cycle

Who approves the room

Your regulator judges the facility, not the contractor. The contractor builds to your room data sheet and supplies test data. To have a room list reviewed, send it to ZY Cleanroom, a cleanroom design-and-build contractor.

Questions

Common questions

What is the biggest running cost of a cleanroom?

Energy, in the studies cited. An LBNL paper from 2001, now dated, cites a European review in which energy cost could reach 65 to 75% of annual operation and maintenance cost.

Does a higher class cost more to run?

In the rooms LBNL measured in its 2001 paper, fan power per area was greater at higher cleanliness. Do not specify a class above what the process needs.

How often are HEPA filters replaced?

No source here sets an interval. Triggers are a failed leak test, uneven velocity, damage, or resistance reaching its final value.

Can I switch the system off at night?

HTM 03-01 calls off the most efficient mode when a space is not in use. In a sterile facility, Annex 1 asks for positive pressure under all operational conditions, so the owner must validate any setback.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.

WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.

Email: [email protected]
WhatsApp: +44 7962 561184

Step 1 of 2

WhatsAppGet a budget range