ZY CleanroomTIANJIN · SINCE 2002 Get a budget range

Buyer guide

The Cleanroom Project Lifecycle

A cleanroom project runs through nine stages: brief and URS, concept and budget, detailed design, manufacture, site build, testing and qualification, handover, routine monitoring, and periodic requalification, with change control whenever the room or its use changes. The owner writes the requirements and approves the results at every stage. The contractor delivers what the contract sets out. The regulator judges the finished facility.

By ZY Cleanroom · Updated · Sources at the end of the page

The stages at a glance

StageWhat happensKey outputWho owns it
1. Brief and URSProcess, room list, target class and site conditions written downURS; scope list and questionsOwner writes; contractor asks questions
2. Concept and budgetLayout, zoning, a first budget to compareConcept layout, budget rangeContractor proposes; owner chooses
3. Detailed designAir balance, pressure cascade, personnel and material flowDrawings, equipment list; DQ where GMP appliesContractor designs; owner approves
4. ManufacturePanels, doors and equipment made or bought in and checkedPacking list, inspection records; FAT where usedContractor
5. Site buildEnclosure, air systems and services installedProgress reports; SAT where usedContractor, with local partners where required
6. Testing and qualificationRoom tests under ISO 14644; IQ, OQ, PQ under GMPTest reportsContractor tests to the contract; owner approves
7. HandoverRecords and training passed to the ownerHandover fileContractor delivers; owner accepts
8. MonitoringParticles, pressure, temperature and humidity watched in useMonitoring recordsOwner
9. Requalification and changePeriodic retests; change control after changesRequalification reportsOwner, often with a test provider

Stages 1 to 2 happen before the contract; stages 3 to 7 are the delivery project; stages 8 to 9 run for the life of the room.

The Cleanroom Project Lifecycle

Stages 1 and 2: brief, URS and budget

The user requirement specification (URS) is the owner's written list of what the room must do. EU GMP Annex 15 treats it as the reference point for the whole project: later design and tests are checked against it. Write each room's class with its occupancy state (as-built, at rest or operational), its pressure, temperature and humidity, and the process it serves. See how to write a cleanroom URS.

A first budget at this stage is a range, not a price. Eight things drive it: class, area and height, air system, temperature and humidity, enclosure, the existing building, testing and documents, and shipping and site work. See what drives cleanroom cost.

Stages 3 to 5: design, manufacture and build

Design. Air volumes come from the room size, people, process and pressure plan, not from the class alone. Where GMP applies, design qualification (DQ) shows the design meets the URS.

Manufacture. Ask which items the contractor makes and which it buys in. On our projects, panels and doors are made in our own factory in Tianjin, and other equipment is checked before shipping.

Site build. The enclosure goes up in a set order: floor track, walls, corners, ceiling, doors and windows, then lights, filters and penetrations, then the final seal and a leak test. See the panel installation guide.

Stages 6 and 7: testing, qualification and handover

ISO 14644-1 sets the particle limits used to classify the room. ISO 14644-3:2019 covers the supporting tests: pressure difference, airflow, airflow direction, recovery, installed filter leakage, and temperature and humidity.

At pharmaceutical sites, EU GMP Annex 1 says cleanroom qualification should follow Annex 15: installation qualification (IQ), operational qualification (OQ) and performance qualification (PQ). Annex 1 para 4.25 lists the qualification tests for sterile manufacturing, and adds airborne and surface microbial contamination, which ISO 14644-3 does not list.

No standard fixes one handover list, so agree it in the contract. It usually includes drawings that match the installation, operating and maintenance instructions, calibration records, materials records and a report for each test. See validation and handover.

Stage 8: monitoring the room in use

A classified room is watched, not only tested once. ISO 14644-2:2015 asks the owner to write a monitoring plan based on a risk assessment: which points, which parameters, which limits, and what happens when a limit is crossed. Typical parameters are airborne particles, pressure difference, temperature and humidity. See cleanroom monitoring systems and pressure alarm troubleshooting.

Stage 9: requalification and change

RoomMaximum requalification intervalSource
GMP Grade A and B6 monthsEU GMP Annex 1, para 4.32
GMP Grade C and D12 monthsEU GMP Annex 1, para 4.32
ISO 5 and cleaner (particle count)6 monthsPublished summaries of ISO 14644-2:2015
ISO 6 and above (particle count)12 monthsPublished summaries of ISO 14644-2:2015
Pharmacy compounding suite (filter leak test)At least every 6 monthsUSP <797>, section 5

Changes restart part of the cycle. A change of final filters is a change to consider for requalification under Annex 1. So is a new process, a new layout or a change in use. Handle these through change control, and retest what the change affects.

When a room no longer meets current rules, the cycle starts again from a new URS. See upgrading an existing cleanroom for Annex 1 and retrofitting a cleanroom in an existing building.

Who is responsible, start to finish

PartyRole across the lifecycle
Owner (manufacturer)Writes the URS, approves protocols and reports, keeps the monitoring and validation programme
ContractorDelivers the contracted scope: design, build, tests and records
Test providerPerforms the tests named in the contract or the monitoring plan; can be independent
RegulatorInspects the owner's facility; does not approve the contractor

GMP approval belongs to the facility and its regulator, not to the contractor.

Questions

Common questions

What are the stages of a cleanroom project?

Brief and URS, concept and budget, detailed design, manufacture, site build, testing and qualification, handover, then monitoring and periodic requalification for as long as the room is used.

How often must a cleanroom be requalified?

For GMP rooms, EU GMP Annex 1 sets a maximum of 6 months for Grades A and B and 12 months for Grades C and D. Published summaries of ISO 14644-2:2015 give 6 months for ISO 5 and cleaner and 12 months for ISO 6 and above.

Who approves a cleanroom at the end of the project?

The owner approves the test results against its URS. At regulated sites, the regulator inspects the facility. The contractor supplies the tests and records.

What is the difference between commissioning and qualification?

Commissioning brings the systems into operation as designed. Qualification under EU GMP Annex 15 documents that the installation (IQ), operation (OQ) and performance (PQ) meet the requirements.

Does replacing HEPA filters mean the room must be retested?

EU GMP Annex 1 lists a change of final filters as a change to consider for requalification. Decide through change control, and at minimum leak-test the new filters in place.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.

WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.

Email: [email protected]
WhatsApp: +44 7962 561184

Step 1 of 2

WhatsAppGet a budget range