Buyer guide

Cleanroom validation and handover: tests, IQ/OQ/PQ and documents

Validation proves that a finished cleanroom meets the owner's written requirements, using ISO 14644 tests and, at pharmaceutical sites, the IQ, OQ and PQ stages of EU GMP Annex 15. The contractor supplies test data and records, the owner approves them, and the regulator, not the contractor, judges the facility.

By ZY Cleanroom · Updated · Sources at the end of the page

Tests under ISO 14644

Particle counting for classification is set out in ISO 14644-1, not in Part 3. ISO 14644-3:2019 covers the supporting tests, in three occupancy states: as-built, at-rest and operational. Its Annex A helps a project choose which tests apply.

Supporting testWhat it shows
Air pressure differencePressure steps between rooms hold as designed.
Airflow, volume and velocitySupply air meets the design figure.
Airflow direction and visualisationAir moves from cleaner to less clean areas.
RecoveryHow fast the room returns to its class after a particle load.
Installed filter system leakageFilters and their seals do not leak.
Temperature and humidityRoom conditions hold as specified.
Cleanroom validation and handover: tests, IQ/OQ/PQ and documents

More tests, and the GMP list

ISO 14644-3 also lists containment leak, electrostatic and ion generator, particle deposition and segregation tests, for rooms where they apply. EU GMP Annex 1 (2022), paragraph 4.25, lists nine qualification tests for sterile manufacturing, where relevant. It adds airborne and surface microbial contamination, which ISO 14644-3 does not list.

IQ, OQ and PQ

EU GMP Annex 15 (2015) describes these stages for the facilities, equipment, utilities and systems of medicinal product manufacturers. Annex 1 says cleanroom qualification should follow Annex 15.

StageWhat it covers
URSThe owner's written requirements, a reference point for the whole project.
DQEvidence that the design meets the URS.
FAT and SATChecks at the vendor and on site, where used.
IQInstallation checked against drawings and specifications, instruments calibrated, materials verified.
OQTests that the system operates as designed, including upper and lower limits.
PQTests that it performs under normal operating conditions, normally after IQ and OQ.

Documents at handover

Annex 15 applies to pharmaceutical manufacturing. Other industries can borrow the stages if the customer specification asks for them.

No standard gives one fixed handover list, so agree the list in the contract. These records follow from the standards above.

DocumentBasis
Drawings that match the installationAnnex 15, IQ (3.9)
Operating and maintenance instructionsAnnex 15, IQ (3.9)
Instrument calibration recordsAnnex 15, IQ (3.9)
Materials of construction recordsAnnex 15, IQ (3.9)
Test reports for each testISO 14644-3:2019, clause 5
Classification results by occupancy stateISO 14644-1:2015
Airflow visualisation recordingsAnnex 1, 4.15 (video recordings retained)
FAT and SAT records, deviation reportsAnnex 15, 2.8 and 3.4 to 3.7

Who is responsible for what

Annex 15 allows data from outside the manufacturer's own programme, such as contractor tests, if the use is justified and controls were adequate when the data were taken.

PartyResponsibility
Owner (manufacturer)Defines the URS, approves protocols and reports, confirms that vendor protocols suit the site, and keeps the validation programme (Annex 15, 1.4, 2.2, 2.6, 3.2).
ContractorDelivers the scope in the contract: design, build, tests and records. ISO 14644-4:2022 does not prescribe the contractual split.
RegulatorInspects the manufacturer. In the EU, the national authority issues a GMP certificate to the manufacturer after inspection (EudraGMDP). FDA does not issue CGMP certificates at the end of an inspection (FDA Data Dashboard).

Next step

To have a room list reviewed, send it to ZY Cleanroom, a cleanroom design-and-build contractor with its own panel and door factory in Tianjin, China.

ISO 14644 certification testing: the steps of a classification run

A classification run, often called certification, follows one order. ISO 14644-1 sets the class limits. EU GMP Annex 1 (25 August 2022) paras 4.26 to 4.29 add that classification is part of qualification, counts particles of 0.5 and 5 µm, and is done at rest and in operation. The owner's quality system, not the test provider, accepts the result.

Worked example: at ISO 7 and 0.5 µm the sample volume is 20 ÷ 352,000 × 1,000 = 0.057 L, so the 2 L minimum governs. A counter drawing 28.3 L/min (1 cubic foot per minute) collects 28.3 L in the 1-minute minimum. At ISO 5 the formula gives 20 ÷ 3,520 × 1,000 = 5.68 L, which the same counter also collects in 1 minute.

StepWhat happensBasis (checked 1 November 2026)
1Agree the class, the occupancy state and the particle sizes in writing.ISO 14644-1:2015; Annex 1 paras 4.27 and 4.29
2Check the particle counter's calibration record.ISO 21501-4:2018 sets the calibration and verification method for light scattering airborne particle counters used for classification
3Set the sampling locations from the floor area.ISO 14644-1 Annex A sets a minimum by area, for example 1 location up to 2 m² and 5 up to 10 m², as reproduced by Pharmaguddu (updated 3 July 2025). Annex 1 para 4.28 adds locations for grade A and B and critical points such as the point of fill.
4Work out the sample volume at each location.Vs = 20 ÷ Cn,m × 1,000 litres, at least 2 L and at least 1 minute per location, as quoted by Beckman Coulter from ISO 14644-1
5Count in the agreed state, scheduled so process and product are not affected.Annex 1 para 4.26; at-rest limits met after a clean-up period, guidance under 20 minutes (para 4.29)
6Compare each result with the Table 1 limit and write the report with the class, the state and the particle sizes.ISO 14644-1:2015, Table 1; Clean Room Technology, tips for ISO 14644-1:2015
7Repeat when due, and after remedial action or changes.Annex 1 para 4.32: at most 6 months for grade A and B, 12 months for grade C and D

Questions

Common questions

Is particle counting part of ISO 14644-3?

No. Classification by particle count is in ISO 14644-1. Part 3 covers supporting tests such as pressure, airflow, recovery and filter leakage.

Who signs off validation?

The owner. Annex 15 says validation documents are approved by personnel defined in the owner's pharmaceutical quality system.

Can a contractor's test data be used for validation?

Yes, if the owner justifies it and controls were adequate when the data were taken (Annex 15, Principle).

Does the contractor get the room approved by the regulator?

No. Regulators inspect the owner's facility and quality system. A contractor supplies the room, the tests and the records.

What is factory acceptance testing for a cleanroom?

Factory acceptance testing checks equipment or assemblies at the vendor's works against an agreed test list before shipping. Faults found there are easier to fix than faults found on site. EU GMP Annex 15 allows some factory tests to count only if transport and installation do not affect the function. Airflow, pressure and particle class still have to be proven in the finished room.

How often should a cleanroom be recertified?

For GMP rooms, Annex 1 sets maximum requalification intervals of 6 months for Grades A and B and 12 months for Grades C and D. Published summaries of ISO 14644-2:2015 give maximum particle count intervals of 6 months for ISO 5 and cleaner, and 12 months for ISO 6 and above. These are upper limits, so set the real frequency in a risk-based monitoring plan.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.

WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.

Email: [email protected]
WhatsApp: +44 7962 561184

Step 1 of 2

WhatsAppGet a budget range