Buyer guide

Installing and commissioning a cleanroom abroad: the site process step by step

On a ZY turnkey project abroad, our own crew travels to site and installs the panels, doors, ceilings, HVAC and cleanroom electrical systems, then commissions the rooms: air handling unit run-in, air balance, pressure cascade, temperature and humidity, and monitoring. The rooms are then tested against the agreed ISO 14644-1 class, and we hand over the test reports, IQ/OQ documents and handover file. Works that need a local licence are carried out by a licensed local contractor named in the contract. The steps below show what happens, in order, and what the owner prepares at each step.

By ZY Cleanroom · Updated · Sources at the end of the page

Step 1. Before shipping: site data and factory release

  • Site data from the owner: the building drawings, measured floor levels, ceiling heights, photographs of the shell, the power supply available, access routes and lifting points. Panels are cut to length at the factory, so the site measurements are fixed before cutting.
  • Factory release: we manufacture the panels and doors in our Tianjin factory, cut them to length and number them to the layout drawing. Other equipment is inspected before shipping. Your inspection company can check the goods before loading.
  • Packing: panels are packed on timber pallets; the packing list follows the panel numbering, so each pallet can be matched to a zone of the layout on arrival.
Installing and commissioning a cleanroom abroad: the site process step by step

Step 2. Shipping and customs

  • The trade term (Incoterms 2020 rule and named place) in the contract sets where delivery happens and who pays for each leg.
  • The importer of record clears customs in your country. Where regulated goods need a conformity certificate, a business licensed in your country applies for it; see the country page for your market.
  • On arrival the pallets are checked against the packing list and stored dry and flat until installation.

Step 3. Visas and arrival of the crew

  • What the owner provides: an invitation letter for the crew's visas, and the site information the visa or work-permit application needs. The visa type depends on your country's rules; we confirm the route with you before the contract.
  • What we provide: the crew's documents, the installation plan and the test protocol.
  • Site induction: the crew takes the owner's site safety induction on arrival and works under the site's permit-to-work rules.

Step 4. Site readiness check

Before installation starts, the crew and the owner walk the site together and record:

ItemReady when
Building shellRoof and walls closed, weather-tight
FloorLevel within the tolerance on the drawings; screed cured
PowerTemporary power at the agreed points
Access and liftingRoute for pallets and the air handling units clear; lifting equipment available
StorageDry, lockable area for panels and equipment
Licensed local worksLicensed local contractor named in the contract, and permits applied for

Step 5. Install sequence

The exact sequence is set in the installation plan for each project. A typical order:

  • Set-out: gridlines and wall lines marked from the layout drawing.
  • Ceiling supports: hangers and support steel for the ceiling grid or walkable ceiling.
  • Wall panels: set in numbered order, with joints sealed as they go. See cleanroom panel installation.
  • Ceiling panels: fixed to the supports; openings for filters, lights and returns cut to the drawing.
  • Doors, windows, pass boxes and air showers: fitted into the prepared openings.
  • HVAC: air handling units placed and connected, ductwork installed and pressure-checked, HEPA filter housings and FFUs mounted. Filters go in after the room is cleaned, so they are not loaded with construction dust. See cleanroom HVAC design.
  • Electrical and controls for the cleanroom systems: lighting, power to the cleanroom equipment, controls and room monitoring. Connections that need a local licence are made by the licensed local contractor named in the contract.
  • Sealing and finishes: joints, penetrations and coving sealed; floor finish laid where it is in the scope (see cleanroom flooring options).
  • Builder's clean, then cleanroom clean: the rooms are cleaned before the final filters are fitted and the air system is started.

Step 6. Commissioning

Our crew commissions the system in this order, and records each result:

CheckWhat is done
AHU run-inFans started and run in; rotation, filter pressure drops and safety interlocks checked
Air balanceSupply and exhaust volumes measured at each room and set to the room data sheet
Pressure cascadePressure differences set between rooms; checked with doors closed and during door opening
Temperature and humidityRoom conditions checked against the room data sheet
Monitoring and alarmsSensors read correctly; alarms raised at the agreed limits
InterlocksAirlock doors, pass boxes and air showers checked for interlock function. See pass box and air shower interlocks

Step 7. Room tests and handover

  • Tests against the agreed class: airflow and air volumes, pressure differences, installed HEPA filter leakage, and airborne particle counts to ISO 14644-1 in the agreed occupancy state. The test methods, and who performs each test, are in the contract. Independent third-party testing can be arranged.
  • Handover documents: test reports, IQ/OQ documents, drawings, equipment list and operating and maintenance information for what we installed. See cleanroom validation and handover.
  • Owner training: the owner's staff are shown how to run the air system, read the monitoring and change filters.
  • Snag list: open items are listed, agreed and closed before final acceptance.

Step 8. After handover

Video support for the owner's maintenance team, and re-testing and maintenance where they are in the contract.

For who does each package on a turnkey contract, see turnkey cleanroom design and build. Chat on WhatsApp (+44 7962 561184) or send your room list.

Questions

Common questions

Who installs the HVAC when a Chinese cleanroom contractor builds abroad?

On ZY turnkey projects, our own crew installs the air handling units, ductwork, HEPA filters and FFUs, and commissions the system. Works that need a local licence are carried out by a licensed local contractor named in the contract.

What does cleanroom commissioning include?

AHU run-in, air balance to the room data sheets, setting the pressure cascade, checking temperature and humidity, and checking monitoring, alarms and interlocks. The rooms are then tested against the agreed class.

What does the owner need to prepare for an overseas installation?

Site data before the panels are cut, a weather-tight shell with a level floor, temporary power, access and lifting, dry storage, an invitation letter for the crew's visas, and the licensed local contractor for works that need a local licence.

When are the HEPA filters fitted?

After the rooms are built and cleaned, so the filters are not loaded with construction dust. The air system is then started and commissioned.

What documents do we receive at handover?

Test reports, IQ/OQ documents, drawings, the equipment list and operating and maintenance information for what we installed.

Do we need separate cleanroom installation contractors, or does your crew install?

On a turnkey contract our own crew installs the panels, doors, ceilings and HVAC and commissions the rooms, so no separate cleanroom installation contractor is needed for that scope. Works that need a local licence are carried out by a licensed local contractor named in the contract. On a design-and-supply or supply-only order, your contractor installs with our numbered drawings and installation guide, and we support the site team by video from set-out to the first panels. On-site supervision can be arranged for larger projects, and installer training can be included in the scope.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.

WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.

Fastest reply: message us on WhatsApp. Or use the form, and add your WhatsApp number so we can reply there.

Email: [email protected]
WhatsApp: +44 7962 561184

Step 1 of 2

Chat on WhatsAppGet a budget range