Cleanroom airlock design: bubble, cascade and sink

An airlock is a small room whose two doors never open together, and its pressure sets which way air moves: a bubble is higher than both neighbours, a sink is lower than both, and a cascade steps down from one side to the other. Choose the type from what must be kept out of the clean room and what must be kept in, then write the pressure steps and door controls into the room data sheet.

By ZY Cleanroom · Updated · Sources at the end of the page

The three types

These are common names for pressure arrangements. Annex 1 para 4.14 allows positively or negatively pressurised airlocks where a hazardous material must be contained.

TypePressureAir movesUse
BubbleHigher than both neighboursOut to both sidesProtect a clean room from a dirtier neighbour
SinkLower than both neighboursIn from both sidesContain a hazardous or potent material
CascadeBetween its neighboursFrom the higher to the lower sideOrdinary steps between grades
Cleanroom airlock design: bubble, cascade and sink

Pressure values

Doors closed. Values are guidance, not a fixed rule.

SourceValue
EU GMP Annex 1, para 4.1410 Pa minimum between adjacent grades (guidance)
FDA, 2004At least 10 to 15 Pa between adjacent rooms of different class; at least 12.5 Pa from an aseptic room to an unclassified room
UK HTM 03-01, Table 6+15 Pa between unclassified rooms and +10 Pa between classified rooms

Doors, flushing and layout

Annex 1 para 4.13 says airlock doors should not open together. It asks for interlocks into grades A and B, and a visual or audible warning into C and D. Add a time delay where segregation needs it.

Para 4.12 asks for personnel and material airlocks to be separate where possible, flushed with filtered air, with the final stage at the same grade at rest as the room it serves. In general, hand washing belongs only in the first stage. Para 4.9 bars sinks and drains in grades A and B.

The CDC and NIH BMBL asks for two consecutive self-closing doors at BSL-3 entry, with a visual device that confirms airflow direction.

Pass-through hatches and cascades

Annex 1 para 4.12 asks that pass-through hatches protect the higher grade, for example by flushing with an active filtered air supply, and that only approved items go through. HTM 03-01 Table 6 shows a cascade in practice: supply only in the clean room, with air leaving through pressure stabilisers to rooms of lower classification.

HTM 03-01 (para 8.18) separates closed-door protection, where leakage flows from clean to less clean, from open-door protection, where airflow through the doorway replaces the lost pressure. Design for both.

Worked example: door leakage

HTM 03-01 Appendix 4 gives closed single-door leakage, assuming gaps of 4 mm at the bottom and 3 mm at top and sides.

Pressure stepLeakage per closed single door
5 Pa0.03 m³/s
10 Pa0.05 m³/s
15 Pa0.06 m³/s
25 Pa0.07 m³/s

What it means for supply air

Example only, calculated from those figures. A bubble airlock 3 m by 2 m and 2.7 m high has 16.2 m³. At a 10 Pa step, two doors leak 2 × 0.05 = 0.10 m³/s, or 360 m³/h. That is 22 air changes before any flushing target.

Pressure does not protect an open door. HTM 03-01 (para 8.17) says a 1.4 m doorway may pass 0.19 m³/s each way with no temperature difference. This is why interlocks and time delays matter.

Who approves the room

Your regulator or customer auditor judges the facility, not the contractor. The contractor builds to your room data sheet and supplies test data. To have a room list reviewed, send it to ZY Cleanroom, a cleanroom design-and-build contractor with its own panel factory in Tianjin, China.

Questions

Common questions

What is the difference between a bubble and a sink airlock?

A bubble is pressurised above both neighbours so air flows out. A sink is below both so air flows in.

Do I need an airlock between every grade?

Annex 1 para 4.12 asks for airlocks for people and materials moving between different grades. Other sectors follow their own specification.

What pressure should an airlock hold?

Annex 1 gives a 10 Pa minimum between adjacent grades as guidance. Set each step in the room data sheet.

Does an airlock need its own air supply?

Annex 1 asks that airlocks be flushed with filtered air so the room grade is kept. The designer sizes the supply.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.

WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.

Email: [email protected]
WhatsApp: +44 7962 561184

Step 1 of 2

WhatsAppGet a budget range