No standard fixes FFU coverage for a class: it follows from the airflow the room needs, divided by what each unit delivers. Published practice runs from 25% to 100% ceiling coverage, and lower coverage means a higher face velocity at each filter and more fan power.

By ZY Cleanroom · Updated · Sources at the end of the page

Start from airflow, not coverage

LBNL defines room air velocity as total supply airflow divided by floor area. It defines air change rate as total supply airflow divided by room volume. It adds that no simple rule links a class to one velocity or one air change rate.

These published values frame the target.

Room typePublished valueSource
ISO 5, unidirectional0.45 m/s ±20%FDA aseptic guidance, 2004
Grade A working position0.36 to 0.54 m/s, guidanceEU GMP Annex 1, para 4.30
ISO 7 pharmacy room30 total HEPA-filtered air changes per hour, at least 15 from ceiling HEPA via the HVACUSP <797> 4.2.4
ISO 8 pharmacy room20 total, at least 15 from ceiling HEPA via the HVACUSP <797> 4.2.4
ISO 8 supporting roomAt least 20 per hour is typically acceptableFDA aseptic guidance, 2004
FFU ceiling layout: coverage, class and grids

Example calculation (assumed values)

Example only, with assumed values. Room: 6 m × 4 m, 3 m ceiling. Floor area is 24 m² and volume is 72 m³. Assume a unit delivers 800 m³/h at its working point. Use your own room size and datasheet value.

ISO 7 at 30 air changes needs 72 × 30 = 2,160 m³/h, or 3 units. ISO 5 at 0.45 m/s needs 0.45 × 24 = 10.8 m³/s, or 38,880 m³/h. That is 540 air changes and 49 units.

The table shows this example ISO 5 case at three coverages. Face velocity equals 10.8 m³/s divided by filter area.

Ceiling coverageFilter area, m²Face velocity, m/s
100%24.00.45
60%14.40.75
40%9.61.13

Ceiling and grid details

USP <797> requires inlaid ceiling panels to be caulked to the support frame, and light fixtures to be flush and sealed. Annex 1 asks for ceilings sealed against contamination from the space above.

Returns in a USP <797> suite must be low on the wall unless a smoke study shows no stagnant air. Repeat the smoke study when equipment moves or the HVAC changes.

Test the finished ceiling

ISO 14644-3:2019 covers installed filter leakage (Annex B.7), airflow velocity and uniformity (B.2), airflow direction and visualisation (B.3) and recovery (B.4).

FDA's 2004 guidance scans the filter face 1 to 2 inches away. A single reading of 0.01% of the upstream challenge signals a significant leak. Annex 1 requalifies Grade A and B every 6 months at most, and Grade C and D every 12.

Put these in the room data sheet

State the class and occupancy state. State the velocity target and where it is measured. State the coverage assumption and the face velocity limit per unit. State how many units may fail before the room fails its class, and give access for aerosol injection and scanning.

Is an FFU ceiling the right system?

LBNL compared recirculation systems in the ISO 5 rooms it reviewed. Fan-tower systems were generally far more efficient than distributed air handlers and FFUs. Efficiency varied widely from room to room.

Efficiency is one factor. Cleanliness class, process risk and maintenance access also count. Compare the options on airflow delivered per watt of fan power, using measured data, before you fix the layout.

Who approves the room

Your regulator judges the facility, not the contractor. The contractor builds the ceiling to your data sheet and supplies test records. To have a room list reviewed, send it to ZY Cleanroom, a cleanroom design-and-build contractor with its own panel factory in Tianjin, China.

Questions

Common questions

How many FFUs does a cleanroom need?

Divide the supply airflow your class needs by each unit's airflow at its working point. Add units only if your data sheet requires a reserve.

What ceiling coverage does ISO 7 need?

No standard gives one. LBNL reports 25% to 100% in practice. Size by airflow, then confirm with a smoke study.

Why does lower coverage cost more energy?

The same airflow passes through less filter area. LBNL says face velocity rises and fan power rises with it.

Can the FFU ceiling be leak tested?

Yes. ISO 14644-3 describes installed filter leakage tests. The design must leave room to inject aerosol and scan.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.