Cleanroom Inspection Checklist: What to Check Before Handover
Inspect a cleanroom in the order it was built: the floor, walls and ceiling for sealed, flush and cleanable surfaces; the doors, windows and pass boxes for fit, seals and interlocks; the air system for filters, airflow direction and pressure; then the test reports and handover documents. A visual walk-through finds most faults before testing, and the tests then prove the class, pressure and filter integrity against the room list.
By ZY Cleanroom · Updated · Sources at the end of the page
Before you start
- Have the approved room list or room data sheet: class and occupancy state, pressure, temperature and humidity for each room.
- Have the current drawings, with revision numbers.
- Agree who inspects, who records, and how faults are logged and closed.
- Inspect with the air system running at its design settings.

1. Floor, walls and ceiling
| Check | Pass when | Basis |
|---|---|---|
| Surfaces | Smooth, impervious and unbroken | EU GMP Annex 1 para 4.5 |
| Recesses and ledges | None that are hard to clean; frames flush with the wall face | Annex 1 para 4.6 |
| Wall-to-floor junction | Coved or sealed joint | USP <797>; FDA 2004 rounded floor-to-wall junctions |
| Panel joints | Even gaps, sealed continuously; no open joint at ceiling or corners | Annex 1 para 4.8; USP <797> |
| Ceiling | Sealed against the space above; inlaid panels sealed to the frame | Annex 1 para 4.8; USP <797> |
| Penetrations | Every cable, pipe and duct opening sealed | Annex 1 para 6.6; USP <797> |
| Sealants and finishes | Named, and suited to the cleaning agents in use | Annex 1 para 4.7 |
| Floor | Smooth, crack-free, no drains where the rules forbid them | Annex 1 para 4.9 (no drains in Grade A and B); USP <797> 4.3.1 |
| Protective film | Removed from all panel faces | Installation guide |
2. Doors, windows and pass boxes
| Check | Pass when |
|---|---|
| Door clear passage | Matches the door schedule in the agreed open position |
| Door frames | Plumb, flush with the wall, sealed all round on both faces |
| Swing and closing | Opens as drawn; closes and latches against the room pressure |
| Door seals | Fitted and continuous |
| Interlocks | Each group tested: one door open keeps the other locked or warns; emergency release works |
| Windows | Flush with the wall face, sealed, glazing as specified |
| Pass boxes | Interlock works; dynamic boxes run and their filter is accessible for testing |
| Air showers | Interlock and cycle work as set; filter access clear |
EU GMP Annex 1 para 4.13 asks for interlocks on airlocks into Grade A and B, and at least a visual or audible warning into Grade C and D. See cleanroom door installation and pass box and air shower interlocks.
3. Air system
| Check | Pass when |
|---|---|
| Terminal filters and FFUs | Installed as drawn, seals seated, labels match the specification |
| Filter leak test access | Every filter can be scanned in place |
| Return grilles | Not blocked by equipment or furniture |
| Airflow direction | Air moves from cleaner to less clean rooms, shown by visualisation |
| Pressure gauges or sensors | Installed between the rooms on the pressure plan, readable, calibrated |
| Alarms | Pressure and other alarms trigger at the agreed limits and reach the right person |
| Temperature and humidity | Hold the room list values |
4. Tests to witness or review
ISO 14644-1 sets the particle limits for classification; ISO 14644-3:2019 sets the supporting tests. Agree in the contract which apply and who performs each.
| Test | Shows |
|---|---|
| Particle count (classification) | The room meets its class in the agreed occupancy state |
| Installed filter leak test | Filters and seals do not leak |
| Air pressure difference | Pressure steps hold as designed |
| Airflow volume or velocity | Supply air meets the design |
| Airflow direction and visualisation | Air moves the right way |
| Recovery | The room returns to its class within the target time |
| Temperature and humidity | Room conditions hold |
| Envelope leak test, if specified | GB 50591-2010 Appendix G gives pressure decay and constant pressure methods |
At pharmaceutical sites, EU GMP Annex 1 para 4.25 adds microbial tests, and qualification follows Annex 15 (IQ, OQ, PQ). See validation and handover and HEPA filter leak testing.
5. Documents in the handover file
| Document | Basis |
|---|---|
| Drawings that match the installation | Annex 15, IQ (3.9) |
| Operating and maintenance instructions | Annex 15, IQ (3.9) |
| Instrument calibration records | Annex 15, IQ (3.9) |
| Materials of construction records | Annex 15, IQ (3.9) |
| A report for each test | ISO 14644-3:2019, clause 5 |
| Classification results by occupancy state | ISO 14644-1:2015 |
| Airflow visualisation recordings | Annex 1, para 4.15 |
| Fault list, with each item closed | Agreed in the contract |
Common faults found on inspection
| Fault | Why it matters |
|---|---|
| Open joint at ceiling or corner | Air and particles pass |
| Unsealed cable or pipe opening | Leak path and cleaning trap |
| Door or window frame proud of the panel face | Ledge that holds dust |
| Door that does not close against the pressure | Pressure cascade fails |
| Interlock bypassed or not wired | Both doors can open together |
| Return grille blocked | Poor airflow and recovery |
| No leak test on record | Leakage unknown |
If a room fails its particle count, see why a cleanroom fails a particle count.
Inspection on our projects
On turnkey projects abroad our own crew installs and commissions the room, and we provide the IQ and OQ documents and the test reports agreed in the contract. Independent third-party testing can be arranged. On supply-only orders, the panels, doors and drawings we manufacture and supply come with an installation guide, and this checklist can be used by your contractor.
The fastest way to start is to chat on WhatsApp (+44 7962 561184); or use our room list builder and the form below.
Questions
Common questions
What should a cleanroom inspection checklist include?
Surfaces and joints of the floor, walls and ceiling; doors, windows, pass boxes and interlocks; filters, airflow direction, pressure and alarms; the tests agreed in the contract; and the handover documents.
When should a cleanroom be inspected?
Walk through it after installation and before testing, with the air system running, so faults are fixed before the particle count. Then witness or review the tests and check the handover file.
Who inspects a cleanroom before handover?
The owner, or someone acting for the owner, inspects against the room list and contract. The contractor performs the agreed tests and supplies the records. At regulated sites the regulator inspects the facility later.
Is a visual inspection enough to accept a cleanroom?
No. The visual check finds build faults. The class, pressure steps and filter integrity are proved only by the tests in ISO 14644-1 and ISO 14644-3.
What documents should I receive at cleanroom handover?
Drawings that match the installation, operating and maintenance instructions, calibration and materials records, a report for each test, and classification results by occupancy state. Pharmaceutical sites add the IQ, OQ and PQ records.
Related guides
- Writing a cleanroom URS: contents and testable wording
- What a cleanroom costs to run: energy, filters and testing
- The Cleanroom Project Lifecycle
- How to audit a cleanroom panel factory, on site or by video
- Turnkey cleanroom contractor
- Room list builder
Sources
- EudraLex Volume 4, Annex 1: Manufacture of Sterile Medicinal Products (published 25 August 2022; applied from 25 August 2023, and from 25 August 2024 for point 8.123; checked 31 October 2026)
- EudraLex Volume 4, Annex 15: Qualification and Validation (Brussels, 30 March 2015, in operation from 1 October 2015; checked 31 October 2026)
- ISO 14644-1:2015, Cleanrooms and associated controlled environments, Part 1: Classification of air cleanliness by particle concentration (published 9 December 2015; checked 31 October 2026)
- ISO 14644-3:2019, Cleanrooms and associated controlled environments, Part 3: Test methods (published August 2019; contents list; checked 31 October 2026)
- Washington State Department of Health, Pharmacy Self-Inspection Worksheet, 2026 USP 797 Sterile Compounding Addendum, DOH 690-296 (January 2026), which reproduces USP <797> text by section; checked 31 October 2026
- FDA, Guidance for Industry: Sterile Drug Products Produced by Aseptic Processing, Current Good Manufacturing Practice (September 2004, nonbinding; checked 31 October 2026)
- GB 50591-2010, Code for Construction and Acceptance of Cleanroom (issued 15 July 2010, in force 1 February 2011; catalogue page; checked 31 October 2026)
Project enquiry
Send what you have
A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.
We reply by email within one working day. We can sign an NDA before you send drawings.
WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.
Fastest reply: message us on WhatsApp. Or use the form, and add your WhatsApp number so we can reply there.
Email: [email protected]
WhatsApp: +44 7962 561184