Cleanroom Inspection Checklist: What to Check Before Handover

Inspect a cleanroom in the order it was built: the floor, walls and ceiling for sealed, flush and cleanable surfaces; the doors, windows and pass boxes for fit, seals and interlocks; the air system for filters, airflow direction and pressure; then the test reports and handover documents. A visual walk-through finds most faults before testing, and the tests then prove the class, pressure and filter integrity against the room list.

By ZY Cleanroom · Updated · Sources at the end of the page

Before you start

  • Have the approved room list or room data sheet: class and occupancy state, pressure, temperature and humidity for each room.
  • Have the current drawings, with revision numbers.
  • Agree who inspects, who records, and how faults are logged and closed.
  • Inspect with the air system running at its design settings.
Cleanroom Inspection Checklist: What to Check Before Handover

1. Floor, walls and ceiling

CheckPass whenBasis
SurfacesSmooth, impervious and unbrokenEU GMP Annex 1 para 4.5
Recesses and ledgesNone that are hard to clean; frames flush with the wall faceAnnex 1 para 4.6
Wall-to-floor junctionCoved or sealed jointUSP <797>; FDA 2004 rounded floor-to-wall junctions
Panel jointsEven gaps, sealed continuously; no open joint at ceiling or cornersAnnex 1 para 4.8; USP <797>
CeilingSealed against the space above; inlaid panels sealed to the frameAnnex 1 para 4.8; USP <797>
PenetrationsEvery cable, pipe and duct opening sealedAnnex 1 para 6.6; USP <797>
Sealants and finishesNamed, and suited to the cleaning agents in useAnnex 1 para 4.7
FloorSmooth, crack-free, no drains where the rules forbid themAnnex 1 para 4.9 (no drains in Grade A and B); USP <797> 4.3.1
Protective filmRemoved from all panel facesInstallation guide

2. Doors, windows and pass boxes

CheckPass when
Door clear passageMatches the door schedule in the agreed open position
Door framesPlumb, flush with the wall, sealed all round on both faces
Swing and closingOpens as drawn; closes and latches against the room pressure
Door sealsFitted and continuous
InterlocksEach group tested: one door open keeps the other locked or warns; emergency release works
WindowsFlush with the wall face, sealed, glazing as specified
Pass boxesInterlock works; dynamic boxes run and their filter is accessible for testing
Air showersInterlock and cycle work as set; filter access clear

EU GMP Annex 1 para 4.13 asks for interlocks on airlocks into Grade A and B, and at least a visual or audible warning into Grade C and D. See cleanroom door installation and pass box and air shower interlocks.

3. Air system

CheckPass when
Terminal filters and FFUsInstalled as drawn, seals seated, labels match the specification
Filter leak test accessEvery filter can be scanned in place
Return grillesNot blocked by equipment or furniture
Airflow directionAir moves from cleaner to less clean rooms, shown by visualisation
Pressure gauges or sensorsInstalled between the rooms on the pressure plan, readable, calibrated
AlarmsPressure and other alarms trigger at the agreed limits and reach the right person
Temperature and humidityHold the room list values

4. Tests to witness or review

ISO 14644-1 sets the particle limits for classification; ISO 14644-3:2019 sets the supporting tests. Agree in the contract which apply and who performs each.

TestShows
Particle count (classification)The room meets its class in the agreed occupancy state
Installed filter leak testFilters and seals do not leak
Air pressure differencePressure steps hold as designed
Airflow volume or velocitySupply air meets the design
Airflow direction and visualisationAir moves the right way
RecoveryThe room returns to its class within the target time
Temperature and humidityRoom conditions hold
Envelope leak test, if specifiedGB 50591-2010 Appendix G gives pressure decay and constant pressure methods

At pharmaceutical sites, EU GMP Annex 1 para 4.25 adds microbial tests, and qualification follows Annex 15 (IQ, OQ, PQ). See validation and handover and HEPA filter leak testing.

5. Documents in the handover file

DocumentBasis
Drawings that match the installationAnnex 15, IQ (3.9)
Operating and maintenance instructionsAnnex 15, IQ (3.9)
Instrument calibration recordsAnnex 15, IQ (3.9)
Materials of construction recordsAnnex 15, IQ (3.9)
A report for each testISO 14644-3:2019, clause 5
Classification results by occupancy stateISO 14644-1:2015
Airflow visualisation recordingsAnnex 1, para 4.15
Fault list, with each item closedAgreed in the contract

Common faults found on inspection

FaultWhy it matters
Open joint at ceiling or cornerAir and particles pass
Unsealed cable or pipe openingLeak path and cleaning trap
Door or window frame proud of the panel faceLedge that holds dust
Door that does not close against the pressurePressure cascade fails
Interlock bypassed or not wiredBoth doors can open together
Return grille blockedPoor airflow and recovery
No leak test on recordLeakage unknown

If a room fails its particle count, see why a cleanroom fails a particle count.

Inspection on our projects

On turnkey projects abroad our own crew installs and commissions the room, and we provide the IQ and OQ documents and the test reports agreed in the contract. Independent third-party testing can be arranged. On supply-only orders, the panels, doors and drawings we manufacture and supply come with an installation guide, and this checklist can be used by your contractor.

The fastest way to start is to chat on WhatsApp (+44 7962 561184); or use our room list builder and the form below.

Questions

Common questions

What should a cleanroom inspection checklist include?

Surfaces and joints of the floor, walls and ceiling; doors, windows, pass boxes and interlocks; filters, airflow direction, pressure and alarms; the tests agreed in the contract; and the handover documents.

When should a cleanroom be inspected?

Walk through it after installation and before testing, with the air system running, so faults are fixed before the particle count. Then witness or review the tests and check the handover file.

Who inspects a cleanroom before handover?

The owner, or someone acting for the owner, inspects against the room list and contract. The contractor performs the agreed tests and supplies the records. At regulated sites the regulator inspects the facility later.

Is a visual inspection enough to accept a cleanroom?

No. The visual check finds build faults. The class, pressure steps and filter integrity are proved only by the tests in ISO 14644-1 and ISO 14644-3.

What documents should I receive at cleanroom handover?

Drawings that match the installation, operating and maintenance instructions, calibration and materials records, a report for each test, and classification results by occupancy state. Pharmaceutical sites add the IQ, OQ and PQ records.

Related guides

Sources

Project enquiry

Send what you have

A room list, a floor plan or only the floor area is enough to start. After you submit, send drawings by email or WhatsApp.

We reply by email within one working day. We can sign an NDA before you send drawings.

WhatsApp +44 7962 561184 is our UK number for export enquiries. The factory is in Tianjin, China.

Fastest reply: message us on WhatsApp. Or use the form, and add your WhatsApp number so we can reply there.

Email: [email protected]
WhatsApp: +44 7962 561184

Step 1 of 2

Chat on WhatsAppGet a budget range